NOX Group took part in renovating the Roland Garros stadium.

The project was organised according to different phases: Reorganising all of the courts, renovating the central court “Phillippe Chatrier” and adding a removable roof. We also had to build a new court with a capacity of 5,000 seats in the “serres d’Auteui”.

We were given a complete mission for conducting operations and assisting work implementation for each of the phases: Preliminary studies and plans, planning permission, main project studies and plans, helping to choose the contracting companies, helping to monitor the work conducted and finally the acceptance procedures.

The project included several 10-month phases on a used site, the work was suspended for two months because of the international tournament in France.